President Nana Addo Dankwa Akufo-Addo has inspected construction work on the Kumasi International Airport, which is expected to be completed in June 2022.
President Akufo-Addo visited the site of the construction on Friday, 1st October 2021, when he commenced his 4-day working visit to the Ashanti Region.
The visit forms part of his annual working visits to all the regions of the country.
The President on 6th June 2018 cut the sod for the commencement of work on Phase Two of the Kumasi Airport Project during which he indicated the expansion is a critical part of the government’s vision to expand the frontiers of the aviation industry in the country, and to realise the dream of making Ghana an aviation hub in West Africa.
President Akufo-Addo was informed the terminal building is 88% complete, the road network 93% complete, the Apron 89% complete, with the air traffic control and rescue and firefighting services 53% complete.
The scope of work include the extension of existing runway pavement from 1,981 metres to 2,320 metres, the construction of a new taxi link and apron, two new apron parking stands, aeronautical ground lighting systems, the design and building of a terminal with the capacity to handle eight hundred thousand passengers per annum, an 11 MW substation, as well the provision of new bulk utility (electricity, water, sewage treatment system, internet etc.) services, independent of the existing utility services for the existing airport facilities.
Phase three (3) of the project involves the construction of the air traffic control building, a fire building station, as well as the expansion of the existing runway pavement. The construction of the fuel farm is to be funded by GOIL.
The project is being constructed by Messrs. Contracta Construction UK Limited with a total project sum of €124.9 million, and financing from Santander, Deutche Bank, and UKEF.
President Akufo-Addo expressed satisfaction with the progress of work undertaken so far, and charged the Ministry of Transport as well as the Contractor to ensure that the October 2022 deadline for completion is met.